GMDA Assures Land for Dwarka Expressway to be Transferred to NHAI in 10 days

GMDA-assures-land-for-Dwarka-Expressway-to-be-transferred-to-NHAI-830x323

Gurugram:  The assurance by Gurugram Metropolitan Development Authority came once the NHAI wrote thereto  seeking the transfer of land in order that work on the Gurugram section of the motorway might begin presently.

The Gurugram Metropolitan Development Authority (GMDA) Tuesday aforesaid that it’d pass land for the Dwarka motorway to the National road Authority of India (NHAI) within the next ten days.

The move comes once the road authority, on Nov nine, wrote to the seeking the transfer in order that work on the Gurugram section of the motorway, that has been delayed for pretty much eight years, might begin presently.

“The possession of land are going to be transferred from Haryana Shahari Vikas Pradhikaran to NHAI inside ten days,” aforesaid Vivek Joshi, CEO, GMDA. “For the allotment of other plots, a reminder has been sent to MD, HSIIDC for early action.” He additionally aforesaid that different problems needed to confirm early begin of labor would even be resolved at the earliest.

The total length of Dwarka motorway is twenty nine kilometer, 18.9 kilometer of that is in Gurugram and therefore the rest in metropolis.

The central authority is building the Dwarka motorway in 5 packages —first package of five.3 kms from knife Murti to road underneath bridge (RuB), second package of four.2 kilometer from RuB to Haryana border, third package of ten.2 kilometer from Haryana border to Basai road over bridge (RoB), fourth package of eight.7 kilometer from Basai RoB to NH-8 – SPR intersection, and therefore the fifth package of five kilometer of Western airdrome property from Dwarka motorway through tunnel.

On Nov nine, NHAI had written to GMDA inquiring for early transfer language that it had entered a contract on Oct twenty three for the event of 2 packages (three and four) in Gurugram that the authority has got to pass encumbrance free work front to the contractor in an exceedingly time-bound manner.

An NHAI official, United Nations agency is aware about the matter, aforesaid that value awarded for section 3 is Rs one,333 large integer and for section four it’s Rs 1047 large integer.

The NHAI had additionally asked GMDA to allot plots to 2 institutions that fall on cardiac resuscitation alignment for clearing the correct of method. Also, an outsized range of trees have to be compelled to be far from the noninheritable land for the motorway, aforesaid the official.

The road authority additionally wished work for prime tension power lines to be completed at the earliest. The authority has additionally wanted details of existing contract entered into by HSVP with the contractors for construction and maintenance of NPR/CPR. “It is requested that the problems mentioned on top of is also resolved at the earliest to avoid any delay, that could lead on to potential liabilities within the execution of the work,” aforesaid the letter.